Target meeting: 05Nov08, 09:00
Present: JT, AN, KL, PH, CB, RN, DK, AD
1. Review of actions:
- PH: Take damaged shaft to TechVac to
show them failed coating and to solicit feedback.
Shaft would have come to RAL for 'transmission' on Tuesday but for illness.
Agreed that a visit to TechVac would be made by PH, EMcC, and JT. The
three of them would coordinate date/time for their own convenience.
- AN: Contact the 'owners' of the
vibration analysis setup at RAL.
AN hadnt done this yet, JT agreed to take action.
- KL: Provide upload link for the next
meeting.
Stands
- KL: Discuss with JR at post explanation
of plots.
Stands.
- All: Send proposed dates for target
workshop and preferred venue.
KL to organise target w/s.
- RH: make inventory of components
available for present target system.
Done, had been sent, KL to post inventory with notes on meeting.
Principal issue is that there is only one set of control electronics.
Need to work towards an operating system in ISIS, R78, and Sheffield.
- CB: Make costing and plan for an
additional control circuitry set up.
Stands. Awaits PS's return from sick leave.
- PS, PH, AD: Calibrate position and
beam-loss response in time for next running period.
Stands. Will be done this week.
- AD, DK, CMacW, JL: Make it possible to
read out the beam-position monitor signal in time for the next running
period.
Stands. Signal has been provided to MICE by D.Wright. At MICE
end there is a need for some signal processing.
- PH: Coordinate target real-time s/w
system and arrange discussion between contributors (JL, P.Hanlet) asap .
Stands. Now an agenda item so this action item will be dropped.
2. Progress
on magnetic measurements
- Stator: CMacW:
Measurements of stator continued with new grounding scheme today.
Noise still observed. CMacW will continue to pursue the measurements,
but, we should decide what to do in the longer term, at next week's meeting.
- Permanent: PH:
Kept for eventual QA.
3. Progress
on mechanical design: JT
JT presented the schedule he had prepared for the
investigation of coatings, target-shaft redesign, build, and installation.
End date (May09) a little late. Important to try and advance this.
Discussion of shape of target shaft concluded by
confirming previous design: hollow cylinder with a flat to stop rotation.
We also discussed the shape of the target blade. It would be convenient if
the shaft could simply extend into the beam. This should be investigated
in s/w. We agreed three actions: JT will send AN the dimensions of the
shaft; AN will seek to simulated the pipe-shaped shaft in Orbit; and MA will
seek to simulate the pipe-shaped shaft in G4BeamLine.
JT commented that tungsten disulphide might be an
appropriate material and noted that it had the advantage that it was applied at
room temperature. JT will continue investigations as to its chemical and
radiaological properties.
PH et all had made initial investigations of shaft motion
with the high speed camera. Shaft is observed to 'kick' or 'flap' at the
end of the stroke. JT suggested moutning an accelerometeer.
Assuming that the results of the target observations with
the high-speed camera indicate that it is worthwhile, we agreed to seek a
retrofit of vibration damping the target system in R78 and running a test.
The benefit of this is that if we find that the vibration damping is important
then it will be possible to retrofit some vibration damping on the target in
ISIS. It is hoped that this will increase the number of dips that are
allowed.
Agreed:
- Goal is to have target with vibration damping running
in R78 during the first week of Dexembe (08!).
4. Progress on (dynamic) mechanical FEA: SY, WL
No report this week: FC review in Oxford.
5. Progress on magnetic FEA: PS
No report this week: PS illness.
6. Upgrading the 'user interface'
Will re-title item 'Target online software' and put PH's
name against it. PH agreed to coordinate contributions from JL and PH and
to interface with JSG and the MICE DAQ.
7. Discussion
No additional items.
8. Date of next meeting
12Nov08: 09:00 -- RAL/phone
9.
AoB
None
Summary of actions:
- PH, EMcC, JT: Take damaged shaft to TechVac to
show them failed coating and to solicit feedback.
- JT: Contact the 'owners' of the
vibration analysis setup at RAL.
- KL: Send proposed dates for target
workshop and preferred venue
- KL: Provide upload link for the next
meeting.
- KL: Discuss with JR at post explanation
of plots.
- KL: to organise target w/s.
- CB: Make costing and plan for an
additional control circuitry set up.
- PS, PH, AD: Calibrate position and
beam-loss response in time for next running period.
- AD, DK, CMacW, JL: Make it possible to
read out the beam-position monitor signal in time for the next running
period.
- JT: will send AN the dimensions of the
shaft;
- AD: will seek to simulated the
pipe-shaped shaft in Orbit;
- MA: will seek to simulate the
pipe-shaped shaft in G4BeamLine.