Target
meeting: 20May09, 09:00
Present: CB, RN, PH, PS, JT, KL, JL, AA
1. Review of actions:
·
JT/RN: Clarify issue of clearance etc. raised above via drawing and email.
JT had sent drawing to RN. 2.4—2.5mm
clearance; need to check tolerances at assembly. Optical housing fit will need to be dealt
with at fit-up. Believed to be possible
to solve the problem by modifying or changing a screw head. OK to carry on.
·
JT/PS: Agree final specification of marker detail.
Done.
·
JT: Modify assembly drawing to show correct orientation of vane.
Done.
·
JT/RN:
Clarify clearance required by connector blocks
and ensure design of cover is commensurate with the required clearance.
Drawing of assembly sent to RN. Only
affects electrical safety covers, which will be retrofitted. So, believe OK to carry on.
·
PH/PS:
Meet with S.Griffiths
et al at DL to discuss details of electrical integration in R78 and ISIS.
Meeting took place yesterday. Make agenda
item on electrical.
·
JT:
Seek to book high-speed camera for relevant
period.
Stands.
·
CB: Collate team’s holiday plans.
Done.
2. Progress on
mechanical design and fabrication:
2.1 Target assembly: JT
·
AC: core parts are being
machined – at point of making final cuts;
·
RH: making bottom flange;
·
Tallirond has been calibrated and used on test pieces;
·
Bearing surface metrology
has been tested – final adjustment to height required;
·
Parts for welding dropped
off at Culham.
Contract not sent (%&*?!!); contractual issue has been addressed.
·
Vacuum tubes brazed and
sent to Sheffield (they have arrived);
·
Stop weld and associated
document complete;
·
Have received veins. Have 40, first one out of packet was of poor
quality. Rest OK, three from the ‘best batch’
sent to Sheffield for test on target rig;
·
All shaft drawings now
released;
·
Grinding order placed
yesterday;
·
Principal worry today is
that delay of order to Culham may have delayed
welding. JT will check today;
·
Material for 2-piece
shaft has still not arrived (%&*?!!). JT will chase.
2.2 Stator: CB
·
Stator has been awaiting
vacuum tube. Tube now there so next job
is to transfer coils on to tube;
·
Resistance check has been
carried out and was OK;
·
Will fit tube in the next
couple of days. Also require retaining
cylinders. JT has sourced the cylinders
and will chase to make sure they get to Sheffield next week;
·
Still on schedule to
supply two stators for CM24.
2.3 Modifications to
gate valve and vacuum vessel: EMcC
·
No report this week.
3. Progress on
electrical installation etc.
·
S.Griffiths will organize power electronics and electrical upgrade in June. Will do equipment in R78 in week beginning
22Jun and equipment in ISIS in week of 29 Jun;
·
Equipment will be
identical so that we have a set of active spares in R78;
·
Some drawings need to be
updated to be completed by the end of June;
·
Thermocouple (K-type)
spare channel is available that terminates in the vac-rack
area;
·
Requested labeling and
documentation of terminations in ISIS to be done. Will check and make inventory at the
beginning of the collaboration meeting.
CB will coordinate with EMcC and JL;
·
Monitoring of chiller: PH
to ask WS of present status;
·
Long fibre-optic
cables: presently at risk because have three runs of cables. Spare fibre-optic
cables were laid. On one route there are
no spare cables. Therefore need to pull
some additional cables as spare;
·
Actions:
o CB: Coordinate with EMcC and JL labeling and
cable documentation.
o PS: Make proposal for fibre spares and get a
quote;
o PH Plan schedule/plan for spare fibre laying
3. Progress on (dynamic)
mechanical FEA: SY, WL
·
No report this week.
4. Progress on magnetic
FEA: PS
·
No report this week.
5. Target electronics
and DAQ: PS, JL
Controller/USBDAQ
interface boards:
·
Progress on board
manufacture, PS will begin work on VHDL coding ~today.
6. Commissioning plan:
discussion
·
Updated version in
preparation. Holidays and details of
schedule being taken into account;
7. Next meeting
·
Next
target meeting: 27May09
·
Next
target w/s, with ISIS: possible dates in June 17 (preferred), 18
1.
ISIS
contributions:
1.
Interlocks/use
of signals on ISIS side;
2.
Beam
loss monitor recording within ISIS;
8. AoB
·
PH: Question about network;
check with Craig MacWaters.
Summary of actions:
·
CB: Coordinate with EMcC and JL labeling and
cable documentation.
·
PS: Make proposal for fibre spares and get a
quote;
·
PH: Plan schedule/plan for spare fibre laying
·
JT:
Seek to book high-speed camera for relevant
period