Target meeting:
30Sep09,
09:00
1. Review of actions:
- PS, JL: write specification for generation
of MICE target signal for ISIS BPS
- PH:
Contact SG to discuss issue and get SG or alternative DL person to next
week's target meeting.
- CB:
will contact EMcC on target coordinates note to allow final MICE Note to be
posted.
2. Progress on
mechanical design and fabrication:
2.1 Target
assembly [2] and [3]: JT
2.2 Stator: CB
3. Progress on electrical
installation etc.: SG
4. Progress on
(dynamic) mechanical FEA: SY, WL
5. Progress on
magnetic FEA: PS
6. Target
electronics and DAQ: PS, JL
7. Target
interaction with MICE PPS and ISIS BPS: CMacW
8.
Documentation, analysis etc.:
9. Planning for installation of T2-prime in R78: All
- PH, can you take on the planning task once again?
9. Next meeting
- 07Oct09: 09:00
- Target workshop in November?
- Remember, second installation jamboree in October!
- Target review meeting with ISIS: 18Dec09 -- is this OK?
10. AoB