Target meeting:
07Oct09,
09:00
Present: PH, CB, PS, RN, JL, JT, KL, SG
1. Review of actions:
- PS, JL: write specification for generation
of MICE target signal for ISIS BPS.
Ongling. Not ready to complete it as yet, see below.
- AN: Try to book high-speed camera for week of 19Oct09
Andy had asked, but not yet received reply. JT will chase. Dont
need high-speed camera until 22Oct09.
- PS: Liaise with SG over making the DL power supply work.
Done. Discussion with SG via email. AO or SG will be at RAL when
assembly and re-commissioning is taking place at RAL.
- AN: Check for clean room facilities in R12
Done. We may use the R12 clean room.
- JT: Check that we may use R2 clean room for assembly
Stands.
- JT: Will estimate Metrology/Microscopy manpower for build
of T2 and inspection.
Done. 25% for September.
- KL: Disseminate date for target meeting with ISIS and MICE
(18Dec09)
Stands. Should be done straight after today's phone call.
2. Progress on
mechanical design and fabrication:
2.1 Target
assembly [2] and [3]: JT
- Shaft and bearings are with TechVac. Machine at TechVac was
'unwell' but is now back in action. The shaft and bearings are now
being prepared for coating. Expecting coatings to be done today.
Expect to take delivery by the end of the week. JT will then have to
inspect so that the shaft/bearings will be ready for Monday.
- Investigation on T2 shaft now complete. Using interferometer at
Taylor Hobson, inspected peak features observed at RAL.
- T2/T3 updates are in hand. Body and top flange for T3 are
manufactured. More discussion on plastics suitable for bearings on T3.
Probably use Vespel and Torlon (spelling?).
2.2 Stator: CB
- No progress since last week. Still about to start testing and
grading coils.
3. Progress on electrical
installation etc.: SG
- Little to report. SG and AO will come to RAL next Tuesday to work
on the controls and PC interface. Sheffield crew will be on site too.
- Schedule shows target commissioning on Wednesday. SG and AO will
discuss and perhaps come to RAL Wednesday instead.
4. Progress on
(dynamic) mechanical FEA: SY, WL
5. Progress on
magnetic FEA: PS
6. Target
electronics and DAQ: PS, JL
- PS:
- Coding has re-started. Presently trying to re-create the
functionality of the present controller in the FPGA. Something
like 70% of the way through this.
- JL:
- Presently working on general controls, so now report.
- PH: Should the s/w in the R78 set up be upgraded? JL believes it
is Ok to leave since upgrades related to the analysis of pulse shape.
7. Target
interaction with MICE PPS and ISIS BPS: CMacW
8.
Documentation, analysis etc.:
- Investigation of T2: JT
- Coordinate note: CB, EMcC
- Note was posted -- MICE Note 263.
- Analysis note: PH [AD]
- Note is about half way through the note.
9. Planning for installation of T2-prime in R78: PH
- Schedule for installation posted here.
9. Next meeting
- 14Oct09: 09:00? Will be working on assembly and commissioning ...
- Agree dont make meeting at 09:00 next Wednesday ... so next meeting
21Oct09
- Target workshop in November?
- Agree will make trgt w.s in November. Propose 27Nov09, confirm
date next week.
- We confirmed the date -- meeting will be in Sheffield
- Target review meeting with ISIS: 18Dec09
10. AoB
None.
Summary of actions
- PS, JL: write specification for generation
of MICE target signal for ISIS BPS.
- JT: Try to book high-speed camera for week of 19Oct09
- JT: Check that we may use R2 clean room for assembly
- KL: Disseminate date for target meeting with ISIS and MICE
(18Dec09)