Target meeting:
06Jan10,
09:00
Present: CB, PH, JL, KL, PS, JT, AD, GB
1. Review of actions:
- PS, JL: write specification for generation of MICE target
signal for ISIS BPS.
Stands.
- GB: To liaise with JT and Shf to work out stator magnetic
QA rig.
Stands.
GB has spoken to Diamond contact with experience in magnetic measurement.
Meeting arranged for this am, snow may cause it to be postponed.
Optimistic that the machine Diamond has available will be suitable.
- KL: To provoke email discussion of readout and analysis of
thermocouple in target housing.
Was done, must be done again -- so, 'stands'. PS will take over action
for January while he's at RAL as MOM.
- AD: will make archive of calibrations on target WWW
site and make code available there too;
This has been done. AD is maintaining it. Action can be removed.
- AD/PH: Will find a way of automating processing so
that BLOC can check the histogram;
Stands.
- PH: Inform trgt group how archiving of target data
to GRID will be done.
Stands.
- AN/KL: Seek additional support for magnetic analysis.
Stands.
- PS: to contact CMacW to ask him to generate a consensus
between MICE and ISIS.
Done.
- PS: When ready in January, ask AN to find an independent
person to review operation of new control system prior to installing it in MLCR.
Stands.
- PS: Look at ways of including the "legal spill" marker
feature.
Stands.
2. Progress on
mechanical design and fabrication:
2.1 Target
assembly [2] and [3]: JT
- Sample of Vespel promised early December. Batch that we were
expecting was deemed to be poor. Next batch will be ready end January.
JT has negotiated supply of material for a slightly increased cost.
- Agreed:
- Start immediately with Torlon while pursuing Vespel and other
materials. Vespel, when it arrives, will displace work on Torlon.
2.2 Stator: CB
- CB spoke to RN to discuss progress on stator. Coils have been
sorted ready for assembly. Should be able to construct stator in next
two weeks;
- TB has proposals to make better coils. Priority of the development
of new coils to be reviewed once magnetic QA and magnetic calculations are
progressed. CB agreed to discuss with TB the magnetic modelling.
3. Target
electronics and DAQ: PS, JL
- PS now at RAL will try and make progress. CB will bring h/w for
new controller to RAL next week.
4. Next meeting
- Wednesday, 13Jan10 at some point during the day when Shf crew arrive.
5.
AoB
6.
Summary of actions
- PS, JL: write specification for generation of MICE target
signal for ISIS BPS.
- GB: To liaise with JT and Shf to work out stator magnetic
QA rig.
- PS: To guide readout and analysis of
thermocouple in target housing.
- AD/PH: Will find a way of automating processing so
that BLOC can check the histogram.
- PH: Inform trgt group how archiving of target data
to GRID will be done.
- AN/KL: Seek additional support for magnetic analysis.
- PS: When ready in January, ask AN to find an independent
person to review operation of new control system prior to installing it in MLCR.
- PS: Look at ways of including the "legal spill" marker
feature.