MICE target phone meeting

15Dec10: 09:00 GMT

Present: EC, JT, KL, CB, PS, JL, PH

1. Review of actions:

         KL: Invite David Findlay to target workshop, and contact Rose to book room.
Half done.KL has invited DF who is away.Room will be organised.

         PH: to produce note on performance of T2.4.
In progress, almost complete.

         PH to contact AH to check pumps can be left on over Christmas.
Believed to be OK. Action can be deleted.

         BS: to measure the field symmetry of T3 about the observed magnetic centre.
Stands.

2. Review of running in R78:

2.1 Latest results: PH, EO

2.2 Discussion: All

3. Progress on mechanical design and fabrication:

3.1 Target assembly [3] and [4]: JT

3.2 Stator development: EC, GB, BS

3.3 Permanent magnet development: PH

3. Target electronics and DAQ: PS, JL

4. Target paper: CB

-       http://mice.iit.edu/bl/Target/index.html

-       No discussion this week.

5. Next meeting

-       Tuesday 21Dec10 10:30/11:00 with inspection close out

6. AoB

Summary of actions

         PH: to produce note on performance of T2.4.

         BS: to measure the field symmetry of T3 about the observed magnetic centre.