MICE target phone meeting
15Dec10: 09:00 GMT
Present: EC, JT,
KL, CB, PS, JL, PH
1. Review of actions:
- PH:
Suggest date for target w/s.
Agreed 21Dec10. KL to book Norton
Room. KL to re-invite David Findlay
or ISIS. Goal is to start at 11:30;
·
KL: Invite David
Findlay to target workshop, and contact Rose to book room.
Half done. KL has invited DF who is
away. Room will be organised.
·
PH: to
produce note on performance of T2.4.
In progress, almost complete.
·
PH to contact AH to
check pumps can be left on over Christmas.
Believed to be OK. Action can be deleted.
·
BS: to
measure the field symmetry of T3 about the observed magnetic centre.
Stands.
2. Review of running in R78:
2.1 Latest results: PH, EO
2.2 Discussion: All
- Generally positive
impression. Keep systematic
checking.
3. Progress on mechanical design and fabrication:
3.1 Target assembly [3] and [4]: JT
- No mechanical report this
week.
3.2 Stator development: EC, GB, BS
- EC has made test piece
for mandrel. Looks as though can
make the mandrel in one piece. Now
proceed to winding test;
- GB to propose schedule
for new stator at target w/s;
3.3 Permanent magnet development: PH
3. Target electronics and DAQ: PS, JL
- PS
- Schematics for board
need to be revised after PS’s tests in the lab;
- Now working on routing
of board;
- EO working on
specification of limits for BPS system;
- JL:
- Now working on routing
of daughter board
- Power supply board
expected to be next week
4. Target paper: CB
- Present draft can be
accessed from:
-
http://mice.iit.edu/bl/Target/index.html
-
No discussion this week.
5. Next meeting
-
Tuesday 21Dec10 10:30/11:00 with inspection
close out
6. AoB
Summary of actions
·
PH: to
produce note on performance of T2.4.
·
BS: to
measure the field symmetry of T3 about the observed magnetic centre.