MICE Scheduling Meeting
|  |
| - |
- Charge (Alain):
- to discuss the consequences of the target failure and the running schedule of MICE between now and March 2012.
The baseline assumption is that we replace the target with a new one in December-January and run with it for the 'EMR run' in March.
The question is if we need some additional running in October-November.
- Agenda:
- Report from Target group: what happened and plans - Paul Hodgson (15')
- What data have been taken in June-July 2011, and what is the present knowledge of the ISIS schedule in Q4 2011 and Q1 2012 — Victoria Blackmore (5')
- Project Manager's comments -- consequences of additional running — Andy Nichols (5')
- EMR plans — Ruslan Asfandiyarov (5')
- Cherenkov needs — Lucien Cremaldi (5')
- TOF needs — Maurizio Bonesini (5')
- AoB
- Discussion
Speakers can upload talks here.
See below for connection details.
Date: Monday, August 8, 2011
Time:
13:00 GMT
Dial-in info: available here.