Tracker Meeting, 27 February 2012
Agenda: minutes
- Actions:
- CMacW: Valve on cryostat needs replacing after accident.
- AD, ES: Commit to spacepoints by the end of the week.
- ES, AD: Split out unpacking/calibration of data in a separate mapper.
- ML, ES, OL, AD, KL: Urgent to add description of the geometry and complete the coordinate system description to the tracker s/w write up.
- CMacW and GB: revise cryostat orientation and check light-guide routing.
- CMacW: to inquire about standard monitoring of fire in racks.
- CMacW: Propose present autodialer system to online group and suggest as the standard for MICE if other systems want them.
- DA, EO: Collaborate on specification of block diagram for delay and distribution of ISIS RF and trigger.
- ABr: Consult re spare VLPC cassettes from D0 as MICE spares.
- DA, ABr: Make plan for implementation of DAQ in Hall.
- KL: Prepare for review of schedules in tracker parallel.
- KL: Make effect of magnetic fields an agenda item.
- CMacW, PR: list all items that may be affected adversely by the magnetic field.
- Particle trigger relationship to ISIS clock: EO
- Cosmic test - status of analysis: ES
- Preparations for single station test and full tracker system:
- Mitigation of effect of magnetic field: CMacW
- Software status
- Snagging list:
- Zero suppression, implies calibration etc.;
- MC responsible person becomes Paul Kybert; need list of jobs;
- Handling of ISIS RF in MICE Hall;
- Implementation of integration window, clock etc. in the MICE Hall;
- Distribution/scheme for handling detector "busy" signals in the MICE Hall;
- Add check sum or other data integrity token to r/o.
- Schedule review
- Next meeting
- Tracker phone call: 05Mar12, 16:30 GMT
- Next Tracker workshops:
- Work-in starting 23Apr12 to get ready for beam test
- Machine physics starts 30Apr12--13May12, then permits and cycle starts 15May12.
- Also need tracker shift pattern.
- Work-in starting 23Apr12 to get ready for beam test
- AoB and summary of actions.